
Using the Point-to-Point Method for Fault Current Calcs
Using the Point-to-Point Method for Fault Current Calculations
A point-to-point fault current calculation is a systematic method used by electricians to determine the magnitude of current that would flow during a short-circuit event at various points in an electrical system. This calculation is crucial for ensuring safety and compliance with NEC 110.24, which requires service equipment in “other than dwelling units” to be field‑marked with the available fault current and the date the calculation was performed. The process typically involves starting at the power source (utility transformer) and sequentially accounting for the impedance of each component the fault current must pass through—transformers, conductors, buswork, and other fixed elements—to find the reduced fault current at downstream points. By accurately determining the AFC, a qualified person (for example, a master electrician or journeyman where permitted by local licensing) can select devices and assemblies with sufficient Short-Circuit Current Rating (SCCR) and interrupting ratings to prevent catastrophic failure and reduce the risk of an Arc Flash Hazard.
Why Accurate Fault Current Calculation is Critical for Electricians
Understanding and calculating the Available Fault Current (AFC) is a fundamental responsibility for any professional electrician. AFC is the maximum current that can be delivered to a point in the system during a short-circuit condition. This is not to be confused with a device’s Amperes Interrupting Capacity (AIC) or an assembly’s Short-Circuit Current Rating (SCCR).
- Available Fault Current (AFC): The amount of current available from the electrical system at a specific point during a fault. This is a calculated value.
- Amperes Interrupting Capacity (AIC) / Interrupting Rating (IR): The maximum fault current that a protective device, like a circuit breaker or fuse, can safely interrupt without being destroyed. This is a device rating. For more on protective devices, see our article on the inverse-time circuit breaker.
- Short-Circuit Current Rating (SCCR): The maximum fault current that an assembly, like a panelboard or motor control center, can safely withstand. This is an equipment assembly rating. The AFC at the point of installation must not exceed the equipment’s SCCR.
The primary driver for these calculations is safety and compliance with the nec code book. Specifically, NEC 110.24 requires service equipment in “other than dwelling units” to be labeled with the available fault current and the date of calculation. This ensures that any installed or replacement equipment has an adequate SCCR, preventing catastrophic failures, fires, and dangerous Arc Flash Hazard events.
Understanding the Point-to-Point Method
The point-to-point method is an application of the Thevenin equivalent principle: the upstream system is represented by an equivalent source and source impedance, and each element downstream contributes series impedance that reduces the available fault current. For practical field and design work, electricians commonly use transformer nameplate data, conductor R and X values, and software or spreadsheets that perform the series-impedance/Thevenin calculations to get the AFC at the downstream point.
Components of a Point-to-Point Fault Current Calculation
To perform the calculation, you must account for everything that impedes the flow of current. The main sources of impedance are the utility source, transformers, and conductors. Additionally, running motors can add current during a fault if they are online at the time of the event.
Source Impedance
The calculation starts at the power source, typically the utility transformer. If the utility provides a short-circuit current or available fault current at the transformer secondary, use that value and document the source. If utility data is not provided, calculate the theoretical three‑phase short-circuit current at the transformer’s secondary from the transformer kVA and nameplate percent impedance (%Z) using the standard conversion: AFC = (kVA × 1000 / (Volts × 1.732)) / (%Z / 100). This gives the starting point for downstream reduction calculations. Correctly identifying this value is a key part of understanding service entrance conductors and NEC rules.
Transformer Impedance
Any time the fault current passes through another transformer, its impedance must be included. Transformer %Z (nameplate) determines how much the transformer limits fault current. Lower %Z means higher potential fault current; for a conservative (worst-case) check, use the minimum %Z within the manufacturer’s tolerance so you evaluate the highest possible AFC the downstream equipment might see.
Conductor Impedance
Conductors have resistance (R) and reactance (X) per length; these values reduce fault current as the distance increases. To include conductor effects correctly, obtain R and X per unit length for the conductor material and size, multiply by the run length to obtain series impedance, and combine that with upstream impedance to compute the downstream AFC. This approach is the standard Series Impedance Calculation used in professional fault‑current studies.
Motor Contribution
Running induction motors can temporarily supply additional current to a fault. Rather than relying on a single universal multiplier, use motor locked‑rotor currents (from the motor nameplate or manufacturer data) or published locked‑rotor tables to determine the motor contribution and add that to the calculated fault current at the device point. If locked‑rotor data are unavailable, an experienced engineer may use conservative approximations for preliminary studies, but final equipment selection should be based on locked‑rotor values or a full short‑circuit analysis.
How to Perform a Point-to-Point Fault Current Calculation (Step-by-Step)
Here is a practical sequence to determine AFC at a downstream panel. This example demonstrates the core logic; many designers use dedicated software to automate the arithmetic and complex phasor math.
- Get Transformer Data and Calculate Initial AFC: Obtain the utility transformer kVA, secondary voltage, and percent impedance (%Z). Calculate the secondary full‑load amperes and then the initial bolted-fault current at the transformer secondary using the three‑phase form: AFC = (kVA × 1000 / (Volts × 1.732)) / (%Z/100). This is your AFC at Point 1.
- Compute Series Impedance of Conductors and Equipment: Determine the R and X of the feeder conductors and of intervening fixed equipment (bus, switch, short lengths of conduit where relevant). Multiply per‑unit length R and X by the conductor length to get series impedance, and add the known impedances of listed equipment where applicable. Use Chapter 9 tables or manufacturer data as the source for conductor impedances, or use a validated calculator.
- Form the Thevenin Equivalent and Solve: Combine the source impedance (from the transformer or utility figure) with the calculated series impedance between Point 1 and Point 2 to form the Thevenin equivalent as seen from Point 2. Solve for the downstream bolted‑fault current using I_fault = V_th / Z_th (phasor algebra). Many software tools perform this automatically.
- Add Motor Contributions: Add the motor locked‑rotor contributions (calculated from nameplate locked‑rotor kVA or locked‑rotor amps, or from manufacturer data) for motors running at the time of fault. When multiple motors are present, use their individual locked‑rotor values; do not rely on a single blanket multiplier if locked‑rotor data are available.
- Verify Equipment Ratings: Compare the final AFC at the device location to the equipment’s SCCR and to the interrupting rating (AIC) of protective devices. The AFC at the point of installation must not exceed the assembly SCCR, and protective devices must have adequate interrupting capacity.
Performing these calculations accurately is a high‑level skill. Master the calculations you’ll need for your contractor’s license exam. ExpertCE offers a range of online electrical courses designed to deepen your understanding of the NEC and complex topics like these.
Key Considerations for Accurate Calculations
While the process can be simplified for a quick check, precision is essential when labeling service equipment or selecting SCCR‑rated assemblies.
- Always Use Worst‑Case Data for Compliance Checks: Use the highest possible AFC when performing a compliance check. For transformer %Z tolerances, use the lowest %Z allowed (which produces the highest fault current) to evaluate the worst-case AFC. When the utility provides a short‑circuit value, document the source and date.
- Account for All Impedance: Include busbars, disconnect switches, and other fixed components in the path, not just conductors. A complete panelboard differs from a load center and has its own impedance characteristics that affect downstream fault currents.
- Document Everything: As required by NEC 110.24, the calculation must be documented and made available. The equipment label should show the AFC (or the method to determine it) and the date of the calculation.
- Update When Systems Change: If major modifications occur—such as changing the utility transformer, adding or removing large motors, or replacing major switchgear—the AFC must be recalculated and labels updated.
Frequently Asked Questions (FAQ)
What is the difference between Available Fault Current (AFC) and Short-Circuit Current Rating (SCCR)?
Available Fault Current (AFC) is the maximum amount of current a system can deliver to a point during a fault. It’s a calculated value for the system. Short-Circuit Current Rating (SCCR) is an equipment rating that specifies the maximum AFC an apparatus or assembly can safely withstand. The AFC must never exceed the SCCR of the equipment it supplies.
Does NEC 110.24 apply to residential dwellings?
No. The requirement in NEC 110.24 for marking service equipment with the available fault current specifically applies to service equipment in “other than dwelling units.” This includes commercial, industrial, and institutional facilities.
How does motor contribution affect a point-to-point fault current calculation?
During a fault, running motors can act as short‑term contributors to fault current because of stored rotational energy and collapsing magnetic fields. Instead of using a universal multiplier, calculate each motor’s locked‑rotor contribution (from nameplate locked‑rotor amps or locked‑rotor kVA) and add those contributions to the system fault current at the point of the fault. If nameplate locked‑rotor data are unavailable, consult the motor manufacturer or engineering references for appropriate guidance.
What is bolted fault current?
Bolted fault current is the theoretical maximum fault current that would flow for a solid (very low impedance) phase‑to‑phase or phase‑to‑ground short circuit. Point‑to‑point methods calculate the realistic bolted‑fault current at the downstream point by accounting for the source impedance and the series impedance of the intervening equipment and conductors. The fault current value is a crucial input for selecting equipment SCCR and for performing an Arc Flash Hazard analysis.
Continuing Education by State
Select your state to view board-approved continuing education courses and requirements:
Disclaimer: The information provided in this educational content has been prepared with care to reflect current regulatory requirements for continuing education. However, licensing rules and regulations can vary by state and are subject to change. While we strive for accuracy, ExpertCE cannot guarantee that all details are complete or up to date at the time of reading. For the most current and authoritative information, always refer directly to your state’s official licensing board or regulatory agency.
NEC®, NFPA 70E®, NFPA 70®, and National Electrical Code® are registered trademarks of the National Fire Protection Association® (NFPA®)


