
Point of Connection Rules for PV Systems (NEC 705.12)
Mastering the Point of Connection for PV Systems: A Guide to NEC 705.12
The correct point of connection for a PV system is a critical decision governed by the National Electrical Code (NEC), ensuring the safety and stability of the electrical system. The NEC provides two general methods for interconnection under Article 705: connections on the supply side of the service disconnect (addressed in 705.11) and connections on the load side of the service disconnect or at distribution equipment on the premises (addressed in 705.12). A common load-side approach is governed by limitations in 705.12, including the provision often called the “120%” condition that constrains the combination of power-source output contribution and the ratings of overcurrent devices relative to the busbar ampacity. Choosing the right point of connection for a PV system is a fundamental skill for electricians, as it prevents dangerous overloads and ensures full compliance with the NEC. A proper load-side calculation or the decision to use a supply-side/service connection is essential for a safe and inspectable installation.
Understanding NEC 705.12: Core Rules for PV System Interconnection
As solar installations continue to rise, every journeyman electrician and master electrician must be an expert in the rules for interconnecting power production sources. Article 705 of the National Electrical Code is the definitive guide for this, and understanding its nuances is non-negotiable. While the entire article is important, Sections 705.11 and 705.12 are the linchpins, detailing the allowable locations for the point of connection PV system. For supplemental discussion and training materials, see the 2023 NEC code book resources.
These rules apply to power production sources operating in parallel with a primary source of electricity (utility-interactive equipment is an example). It’s important to distinguish these from legally required or optional standby systems; the NEC treats standby/emergency arrangements separately from the parallel-interconnection rules in Article 705.
NEC 705.11: The Supply-Side Connection Explained
A supply-side connection under 705.11 is an interconnection to the service; 705.11 permits connections to a new service, the supply side of the service disconnecting means, or an additional set of service entrance conductors, as allowed by the code. Where a supply-side/service connection is made, the connections must comply with the requirements of 705.11, including conductor sizing and overcurrent protection as required by Part VII of Article 230 and 705.11(B)–(F). For supplemental discussion of service entrance topics, you may find this service entrance resource helpful.
Key Requirements for a Supply-Side Tap
Connecting on the line side of the main disconnect is a major undertaking that must be done with precision. 705.11 identifies the permitted service-connection methods and 705.11 and related provisions in Article 230 and Article 705 address conductor sizing, overcurrent protection, and utility-controlled equipment considerations. It is crucial for installers to remember that these tapped conductors may be energized when the utility is present, regardless of the position of the main service disconnect. This elevates the risk and underscores the importance of proper installation, including a dedicated PV system disconnecting means and robust PV system labeling to warn of multiple power sources (see Article 705 disconnect and marking requirements).
NEC 705.12: Mastering the Load-Side Connection
A common method for residential PV interconnections is a load-side connection addressed in 705.12. This involves connecting the output of an interactive inverter to the load side of the service disconnecting means or to distribution equipment on the premises. Before starting, it’s crucial to understand the equipment you’re working with, including the differences between a load center and a panelboard, as this can affect busbar construction and connection options; for background material see load center vs a panelboard.
The 120%-Type Conditions and Busbar Rating Calculations
One key limitation for load-side connections appears in 705.12: in general 705.12(B)(1) requires that the sum of 125 percent of the power-source output circuit current and the rating of the overcurrent device protecting the busbar shall not exceed the busbar ampere rating; for the specific case where two sources (one primary and one other) are located at opposite ends of a busbar, 705.12(B)(2) provides the condition commonly referred to as a “120%” evaluation. Performing the load-side calculation is the required process under 705.12 and 705.28 (circuit sizing) and 705.30 (overcurrent protection).
- Step 1: Determine the Busbar Rating and Main OCPD. Identify the ampere rating of the busbar and the rating of the overcurrent device protecting the busbar from the panel equipment label (do not assume the busbar rating equals the main device rating).
- Step 2: Calculate the allowed 125% contribution. Using the opposite-ends condition from 705.12(B)(2), calculate the expression (1.2 × busbar ampacity) − (rating of the overcurrent device protecting the busbar). That result is the maximum value allowed for 125% of the power-source output circuit current. For a 200 A busbar with a 200 A main device, the calculation is (1.2 × 200 A) − 200 A = 40 A.
- Step 3: Determine Maximum Inverter Output Current. Divide the result from Step 2 by 1.25 (to remove the 125% factor). In the example: 40 A ÷ 1.25 = 32 A.
- Step 4: Select inverter and overcurrent protection. Determine the inverter continuous output current from Step 3 (32 A in the example) and size the overcurrent device in accordance with the overcurrent protection requirements of Article 705 and Article 240. Article 705 requires that power-source output conductors and equipment have overcurrent protection and 705.30(B) indicates overcurrent devices typically be rated not less than 125% of the maximum currents calculated in 705.28(A). In the example, the 125% rule applied to the inverter continuous current (32 A × 1.25 = 40 A) results in a 40 A device rating as the corresponding device rating to protect those conductors and equipment consistent with the code provisions.
Center-Fed Panelboard Considerations
705.12 includes options addressing how multiple sources are combined. One of the conditions that enables a particular evaluation (often described as the “opposite ends” condition) requires that the two sources be located at opposite ends of the busbar; under that circumstance the code provides the 120% type criterion in 705.12(B)(2). Where sources are not located at opposite ends, 705.12 provides other options. For equipment without a specific listing for combining multiple sources, 705.12(B)(1) and 705.12(B)(3) include alternative methods to determine busbar ampacity and limitations; for example, 705.12(B)(3)(3) states that the sum of the ampere ratings of all overcurrent devices on panelboards, both load and supply devices, excluding the rating of the overcurrent device protecting the busbar, shall not exceed the ampacity of the busbar.
Feeder Taps as a Load-Side Option
705.12 permits output of an interconnected electric power source to be connected to the load side of the service disconnecting means or at distribution equipment on the premises; where the power source output connection is made to a feeder, 705.12(A) through (B) enumerate requirements that apply to feeders and feeder taps, and the referenced tap rules in Article 240 (e.g., 240.21) are relevant to feeder tap sizing and protection.
Critical Safety Components for Any Point of Connection PV System
Regardless of the connection method, several safety systems are required or referenced by the NEC for grid-tied PV installations. These systems work together to protect personnel and equipment.
PV System Disconnecting Means and Overcurrent Protection
Article 705 requires means to disconnect power source output conductors from conductors of other systems; a single disconnecting means may be permitted to disconnect multiple power sources. The disconnecting means must meet the enumerated requirements (manually operable switch or breaker, simultaneously disconnect all ungrounded conductors, be readily accessible, externally operable without exposed live parts, indicate open/closed, and have ratings sufficient for maximum circuit current and available fault current) as described in 705.20. The power-source output conductors and equipment must be provided with overcurrent protection as required elsewhere in Article 705 and Article 240; see 705.30 and 705.28 for overcurrent and conductor sizing provisions.
Arc-Fault and Other Branch Protections
Article 690 requires photovoltaic system dc circuits operating at 80 volts dc or greater between any two conductors be protected by a listed PV arc-fault circuit interrupter or other listed component providing equivalent protection (690.11). The AC output of an interactive inverter is addressed under Article 705 interconnection rules and general AC overcurrent protection (705.30); additional branch-circuit AFCI or GFCI requirements are governed by other applicable NEC articles such as Article 210 for dwelling-unit branch-circuit AFCI rules and Article 210 for GFCI locations.
Rapid Shutdown and PV System Labeling Requirements
Article 690 requires rapid shutdown functions for PV systems installed on or in buildings to reduce shock hazard for emergency responders; 690.12 sets controlled conductor limits, initiation device location, labeling, and other requirements for rooftop installations and circuits on buildings. Proper equipment grounding and durable, code-required labeling at disconnects and distribution equipment are required by the NEC to indicate multiple sources and to facilitate safe operation and maintenance.
- Key Takeaways:
- NEC provides two main options for a PV system point of connection: supply-side (705.11) and load-side (705.12).
- Load-side connections are limited by the conditions in 705.12, which include the 125%/120% style evaluations used to protect the busbar rating in certain configurations.
- A supply-side/service connection is an alternative when the load-side limitations cannot be met but requires careful adherence to the service connection rules in 705.11 and Article 230.
- The position of a back-fed circuit breaker and the specific busbar configuration affect which 705.12 option applies; where sources are at opposite ends the 705.12(B)(2) condition applies, otherwise other 705.12 options must be considered (including the sum-of-device-rating constraint in 705.12(B)(3)).
- All interconnected systems require an appropriate PV-system disconnecting means, overcurrent protection sized per the code, and clear labeling as specified in Article 705 and related articles.
The rules for interconnection are complex and codified in Article 705 and related articles (including Article 240 for tap and overcurrent rules, Article 690 for PV-specific DC and rapid-shutdown requirements, and Article 110 for marking and disconnect requirements). For additional guidance and training materials, you may find this NEC update resource helpful. Make the right connection every time. Master NEC 705 with continuing education and by consulting the NEC text when designing or installing interconnected systems.
Frequently Asked Questions (FAQ)
- What is the 120%-type condition for a point of connection pv system?
- The 120%-type condition is a calculation used for certain load-side connections (for example, when two sources are located at opposite ends of a busbar). Under 705.12(B)(2), the code limits the combination of 125% of the power-source output circuit current and the rating of the overcurrent device protecting the busbar relative to the busbar ampacity as provided in the Article 705 text.
- When should I use a NEC 705.11 supply-side connection instead of a load-side connection?
- A supply-side/service connection (705.11) is used when a load-side connection is not feasible under 705.12 limitations for the existing distribution equipment; the code permits supply-side service connections in 705.11 as an alternative method of connection.
- Does NEC 705.12 apply to a solar powered generator for home with a transfer switch for generator?
- No. Article 705 applies to sources operating in parallel with the primary source. Standby systems that supply loads separated from the grid by transfer means are addressed under their respective NEC articles for standby/emergency systems and not treated as parallel-interconnected generation under Article 705.
- How does the busbar rating affect my load side calculation?
- The busbar ampacity is fundamental to the load-side evaluation under 705.12. The calculations in 705.12 reference the busbar ampacity (not only the main-device rating), so verify the busbar ampacity on the equipment nameplate and apply the appropriate 705.12 provisions for the configuration you are evaluating.
Continuing Education by State
Select your state to view board-approved continuing education courses and requirements:
Disclaimer: The information provided in this educational content has been prepared with care to reflect current regulatory requirements for continuing education. However, licensing rules and regulations can vary by state and are subject to change. While we strive for accuracy, ExpertCE cannot guarantee that all details are complete or up to date at the time of reading. For the most current and authoritative information, always refer directly to your state’s official licensing board or regulatory agency.
NEC®, NFPA 70E®, NFPA 70®, and National Electrical Code® are registered trademarks of the National Fire Protection Association® (NFPA®)


