
Point of Connection Rules for PV Systems (NEC 705.12)
Mastering the Point of Connection for PV Systems: A Guide to NEC 705.12
The correct point of connection for a PV system is a critical decision governed by the National Electrical Code (NEC), ensuring the safety and stability of the electrical system. The code dictates two primary methods for interconnection: a NEC 705.11 supply-side connection, made between the meter and the main service disconnect, and a NEC 705.12 load-side connection, typically to the busbar of a breaker panel. The most common method, the load-side connection, is governed by the “120% rule,” which limits the amount of back-fed power to protect the busbar rating. Choosing the right point of connection for a PV system is a fundamental skill for electricians, as it prevents dangerous overloads and ensures full compliance with the NEC. A proper load-side calculation or the decision to use a supply-side tap is essential for a safe and inspectable installation.
Understanding NEC 705.12: Core Rules for PV System Interconnection
As solar installations continue to rise, every journeyman electrician and master electrician must be an expert in the rules for interconnecting power production sources. Article 705 of the National Electrical Code is the definitive guide for this, and understanding its nuances is non-negotiable. While the entire article is important, Sections 705.11 and 705.12 are the linchpins, detailing the allowable locations for the point of connection PV system. Keeping up with changes in the 2023 NEC code book is vital, as it continues to refine these rules for clarity and safety.
These rules apply specifically to systems using a utility interactive inverter, which is designed to operate in parallel with the electric utility. It’s important to distinguish these from legally required or optional standby systems, which often use a transfer switch for generator or a generator interlock kit and are covered by Articles 700, 701, and 702. While a solar powered generator for home might be part of an energy storage system, if it’s interacting with the grid, its connection point falls under Article 705.
NEC 705.11: The Supply-Side Connection Explained
A NEC 705.11 supply-side connection, often called a supply side tap, is an interconnection made on the supply side of the main service disconnecting means. In simple terms, you are tapping the conductors between the utility meter and the main breaker of the service panel. This method is often the go-to solution when a load-side connection is not feasible, particularly in situations where the existing breaker panel cannot accommodate the solar inverter’s output without violating the 120% Rule, which is common in older homes or with a fully loaded 200 amp panel.
Key Requirements for a Supply-Side Tap
Connecting on the line side of the main disconnect is a major undertaking that must be done with precision. The conductors for the tap must be sized appropriately and protected by their own overcurrent protection device (OCPD). The rules governing these connections are stringent and closely mirror those for service entrance conductors. It is crucial for installers to remember that these tapped conductors are energized whenever the utility is present, regardless of the position of the main service disconnect. This elevates the risk and underscores the importance of proper installation, including a dedicated PV system disconnecting means and robust PV system labeling to warn of multiple power sources.
NEC 705.12: Mastering the Load-Side Connection
The most common method for residential PV interconnections is the NEC 705.12 load-side connection. This involves connecting the output of the utility interactive inverter to the load side of the service disconnecting means, typically by installing a back-fed circuit breaker in the main service panel. Before starting, it’s crucial to understand the equipment you’re working with, including the key differences between a load center vs a panelboard, as this can affect busbar construction and connection options.
The 120% Rule and Busbar Rating Calculations
The cornerstone of a compliant load-side connection is the “120% Rule,” found in NEC 705.12(B)(3)(2). This rule is designed to protect the panel’s busbar from being overloaded by the combined power from the utility and the PV system. It states that the sum of the overcurrent device rating protecting the busbar (the main breaker) plus 125 percent of the power source output circuit current shall not exceed 120 percent of the busbar ampacity. Performing the load side calculation is a mandatory process.
- Step 1: Determine the Busbar Rating and Main OCPD. Identify the ampere rating of the busbar and main breaker from the panelboard’s label. Do not assume the busbar rating is the same as the main breaker.
- Step 2: Calculate Maximum Allowable Power Source Contribution. Multiply the busbar rating by 1.2, then subtract the main OCPD rating. This result is the maximum value allowed for “125% of the power source output circuit current.” For a 200A busbar with a 200A main breaker, this is (200A x 1.2) – 200A = 40A.
- Step 3: Determine Maximum Inverter Output Current. Divide the result from Step 2 by 1.25. This gives you the maximum continuous current the inverter is allowed to supply. In our example: 40A / 1.25 = 32A.
- Step 4: Select the Inverter and Breaker Size. Choose an inverter with a continuous output current of 32A or less. The back-fed breaker must be sized for this output. Note: Per NEC 705.28(A), the back-fed breaker must be rated for at least 125% of the inverter’s continuous output current (32A x 1.25 = 40A), making a 40A breaker the maximum size allowed in this scenario.
Center-Fed Panelboard Considerations
The 120% rule includes a critical provision for positioning the back-fed breaker. To prevent overloading any single point on the busbar, the power source OCPD must be located at the opposite end of the panel from the main breaker or main lugs. This arrangement becomes more complex in busbar configurations where the sources are not at opposite ends, such as a center-fed panelboard where the main breaker is in the middle. For these busbars, NEC 705.12(B)(3)(3) clarifies that an interconnection is permitted only if the sum of the ampere ratings of all overcurrent devices on the panel, excluding the main supply OCPD, does not exceed the ampacity of the busbar.
Feeder Taps as a Load-Side Option
In some cases, especially in commercial applications, connecting directly to the panelboard busbar is not practical. NEC 705.12(A) also permits a load-side connection to be made via a feeder tap. This allows the PV system to connect to the feeder conductors that supply a panelboard, provided the connection complies with the tap rules in NEC 240.21(B).
Critical Safety Components for Any Point of Connection PV System
Regardless of the connection method, several safety systems are mandatory for any grid-tied PV installation. These systems work together to protect personnel and equipment.
PV System Disconnecting Means and Overcurrent Protection
Every PV system requires a specific PV system disconnecting means to isolate it from all other conductors in the building. This disconnect must be clearly labeled and readily accessible. Likewise, the PV system output circuit must have its own overcurrent protection device (OCPD), such as a fuse or circuit breaker, sized correctly for the inverter’s output. Per 2023 NEC 690.11, listed DC arc-fault protection is required for PV systems with DC circuits on or in a building operating at 80 volts or greater. While Article 690 does not mandate this for the AC output of inverters, an arc fault circuit breaker (AFCI) may still be required for the AC branch circuit depending on the location, such as in dwelling units per NEC 210.12.
Rapid Shutdown and PV System Labeling Requirements
In addition to connection rules, rapid shutdown requirements (NEC 690.12) mandate a method for first responders to de-energize the PV system conductors on and in the building. Proper installation of the equipment grounding conductor (EGC) is also fundamental for safety. Finally, clear and durable PV system labeling is required at the disconnects and point of connection, warning of the presence of an active power production source.
- Key Takeaways:
- NEC provides two main options for a PV system point of connection: supply-side (705.11) and load-side (705.12).
- Load-side connections are limited by the 120% rule, which protects the panel’s busbar rating.
- A supply-side connection is an alternative when the 120% rule cannot be met but requires careful adherence to rules for service conductors.
- The position of the back-fed circuit breaker in the panel is critical and must be at the opposite end from the main feed for the 120% rule to apply, posing a challenge for a center-fed panelboard.
- All interconnected systems require a dedicated PV system disconnecting means, OCPD, and clear labeling.
The rules for interconnection are complex and continue to evolve with technology and safety standards. Recent updates in the NEC have provided more options, including rules for Energy Management Systems in the new section 705.13. To dive deeper into these changes, explore how the 2023 NEC update addresses interconnection and transfer equipment. Make the right connection every time. Master NEC 705 with our courses.
Frequently Asked Questions (FAQ)
- What is the 120% rule for a point of connection pv system?
- The 120% rule, found in NEC 705.12(B)(3)(2), is a calculation used for load-side connections where the power sources are at opposite ends of a busbar. It states that the sum of the main breaker’s rating plus 125% of the PV system’s continuous output current cannot exceed 120% of the panelboard’s busbar rating. This prevents the busbar from being subjected to more amperage than it is designed to handle.
- When should I use a NEC 705.11 supply-side connection instead of a load-side connection?
- A supply-side connection is used when a load-side connection is not possible. The most common reason is that the required PV system back-fed breaker is too large to meet the 120% rule for the existing breaker panel, such as a 200 amp panel that is already at its limit for a load-side connection.
- Does NEC 705.12 apply to a solar powered generator for home with a transfer switch for generator?
- No. NEC 705.12 applies to utility-interactive systems that operate in parallel with the grid. A system using a transfer switch for generator is typically a standby system (covered under NEC Articles 700, 701, or 702), which is designed to power loads separately from the grid, not simultaneously with it.
- How does the busbar rating affect my load side calculation?
- The busbar rating is the foundation of the load side calculation. The entire 120% rule is based on this rating, not the rating of the main breaker. A higher busbar rating allows for a larger PV system to be connected on the load side. You must always verify the busbar rating from the panel’s label.
Continuing Education by State
Select your state to view board-approved continuing education courses and requirements:
Disclaimer: The information provided in this educational content has been prepared with care to reflect current regulatory requirements for continuing education. However, licensing rules and regulations can vary by state and are subject to change. While we strive for accuracy, ExpertCE cannot guarantee that all details are complete or up to date at the time of reading. For the most current and authoritative information, always refer directly to your state’s official licensing board or regulatory agency.



