
Transformer Grounding and Bonding Under the 2023 NEC
Transformer Grounding and Bonding Under the 2023 NEC: A Guide to Article 250 and 450
Properly applying NEC 2023 grounding and bonding rules to transformers is one of the most critical tasks for an electrician. For a Separately Derived System (SDS)—where a transformer creates a new, electrically independent power source—the 2023 National Electrical Code (NEC) in Article 250, specifically NEC 250.30, mandates a precise methodology. The core requirement is to establish a solid reference to ground and create a low-impedance effective ground-fault current path. This is achieved by installing a System Bonding Jumper (SBJ) to connect the grounded conductor (neutral) to the equipment grounding system, and a Grounding Electrode Conductor (GEC) to connect the grounded conductor to a suitable grounding electrode system. These connections establish the ground reference, stabilize voltage, and ensure an Overcurrent Protective Device (OCPD) can operate swiftly during a fault, safeguarding both personnel and equipment.
Foundational Principles: Why Proper Grounding and Bonding Matters
Before diving into the specifics of NEC Article 250 and Article 450, it’s crucial to understand the fundamental safety principles at play. The primary purpose of system grounding is to limit the voltage imposed by lightning, line surges, or unintentional contact with higher-voltage lines, and to stabilize the voltage to earth during normal operation. Bonding, on the other hand, is about ensuring electrical continuity between all metallic components in a system that are likely to become energized.
When combined correctly, these two concepts create an effective ground-fault current path. This is a low-impedance path designed to carry fault current from the point of a fault back to the electrical source, enabling the OCPD to open and clear the fault. A failure in this path can lead to energized equipment, fire hazards, and severe electrical shock. This principle is so fundamental that specific applications, such as healthcare facilities, have their own detailed requirements. The 2023 NEC clarifies equipment grounding in healthcare spaces to ensure patient and staff safety.
Is Your Transformer a Separately Derived System?
The first and most important determination is whether your transformer installation qualifies as a Separately Derived System (SDS). The NEC defines an SDS in Article 100 as “an electrical source, other than a service, having no direct connection(s) to circuit conductors of any other electrical source other than those established by grounding and bonding connections.”
In simpler terms, if the transformer secondary has no direct electrical connection to the primary supply conductors (except for the Equipment Grounding Conductor – EGC), it’s an SDS. The most common example is a standard delta-wye isolation transformer. The secondary wye creates a new neutral point that must be grounded. Conversely, an autotransformer, which shares a common winding, is typically NOT a separately derived system.
This distinction is critical because all the rules in NEC 250.30 apply specifically to the grounding and bonding of an SDS.
Key Components for NEC 2023 Grounding and Bonding of a Separately Derived System
Once you’ve identified an SDS, NEC 250.30(A) outlines the required components for a compliant installation.
The System Bonding Jumper (SBJ)
The System Bonding Jumper (SBJ) is the electrical link between the system’s grounded conductor (neutral) and the supply-side bonding jumper, the non-current-carrying metal enclosure, and the equipment grounding conductor(s). Its sole purpose is to create the link needed for the effective ground-fault current path. Per 250.30(A)(1), this connection must be made at only one point—either at the source (the transformer) or at the first system disconnecting means. Making this connection at more than one point would create parallel paths for neutral current, resulting in objectionable current on grounding conductors.
The Grounding Electrode Conductor (GEC)
The Grounding Electrode Conductor (GEC) connects the grounded conductor of the derived system to the grounding electrode system. This connection establishes the system’s reference to earth. The GEC is sized based on the total circular mil area of the derived ungrounded phase conductors, according to NEC Table 250.66. The GEC connection to the grounded conductor must be made at the same point where the System Bonding Jumper is installed.
The Grounding Electrode System
Per 250.30(A)(4), the grounding electrode must be as near as practicable to the GEC connection point. The code requires this electrode to be one of the following, in order of preference:
- The nearest effectively grounded building steel.
- The nearest effectively grounded metal water pipe.
- Other electrodes as specified in 250.52 if the above are not available.
It’s important to note that you do not necessarily need a new, separate electrode (like a ground rod) if a qualified building ground is accessible and available.
Step-by-Step: Sizing the System Bonding Jumper (SBJ)
Correctly sizing the SBJ is non-negotiable for code compliance. The process follows the rules outlined in NEC 250.102(C), which directs you to Table 250.102(C)(1).
- Determine the Size of the Derived Conductors: Identify the size (in kcmil or AWG) of the ungrounded secondary conductors being supplied by the transformer. If conductors are run in parallel, you must use the total circular mil area of the parallel conductors for each phase.
- Reference NEC Table 250.102(C)(1): Find your conductor size (or equivalent total area) in the left column of the table. The right column will specify the minimum required size for your copper or aluminum SBJ.
- Apply the 12.5% Rule (for large conductors): If the total circular mil area of your ungrounded conductors exceeds 1100 kcmil (copper) or 1750 kcmil (aluminum), the SBJ size must be at least 12.5% of the area of the largest ungrounded phase conductor. Sizing the Equipment Grounding Conductor (EGC) often involves similar principles and calculations. For a detailed review of recent updates, learn how EGC sizing and splicing rules have changed in the 2023 NEC.
Critical Considerations for a Code-Compliant Installation
Achieving compliant NEC 2023 grounding and bonding goes beyond just connecting wires. Here are key takeaways for your next transformer installation:
- Single Point of Connection: The SBJ and GEC must connect to the grounded conductor at the same, single point. This prevents objectionable current from flowing on your EGCs and metal piping systems under normal operating conditions.
- The Supply-Side Bonding Jumper (SSBJ): Remember that an effective fault path requires a connection back to the source. The Supply-Side Bonding Jumper (SSBJ), often the metal raceway or a wire-type EGC run with the primary feeders, completes this critical path.
- Physical Protection: Both the GEC and the SBJ must be protected from physical damage. If enclosed in a ferrous metal raceway, the raceway must be bonded at both ends to prevent it from acting as an inductor (choke) during a fault event.
- High-Impedance Grounding: While this article focuses on the common solidly grounded system, be aware that for systems 480V to 1000V, high-impedance grounding is permitted under specific conditions outlined in 250.36 and 250.187. This specialized application is used to control fault current levels in industrial settings.
Staying current with these intricate rules in NEC Article 250 and NEC Article 450 is essential for every professional electrician. To ensure your knowledge is up-to-date for your license renewal, Complete your CE renewal online at ExpertCE.
Primary Sources for NEC Compliance
This article is based on the requirements found in the 2023 National Electrical Code (NEC), also known as NFPA 70. For official information, always consult the latest edition of the code published by the National Fire Protection Association (NFPA).
Frequently Asked Questions (FAQ)
What is the main purpose of NEC 2023 grounding and bonding for a transformer?
The main purpose is to create a safe electrical system by establishing a stable reference to ground and providing an effective ground-fault current path. This ensures that an overcurrent device will operate quickly to de-energize the circuit during a ground fault, preventing shock hazards and equipment damage.
Where should the System Bonding Jumper (SBJ) be installed for a Separately Derived System?
According to NEC 250.30(A)(1), the System Bonding Jumper (SBJ) must be installed at one location only. This can be at the transformer itself or in the first disconnecting means or overcurrent device located on the secondary side of the transformer.
How do I size the Grounding Electrode Conductor (GEC) for a transformer?
The Grounding Electrode Conductor (GEC) for a Separately Derived System is sized based on the total circular mil area of the derived ungrounded phase conductors. You must use NEC Table 250.66 to determine the correct size of the GEC based on this calculation.
Do I need a new grounding electrode for every transformer?
Not necessarily. NEC 250.30(A)(4) directs you to use the nearest available and effectively grounded building structural steel or metal water pipe as the grounding electrode. A new electrode (like a ground rod) is only required if these preferred electrodes are not available.
About ExpertCE
At ExpertCE, we specialize in providing high-quality, state-approved continuing education courses for licensed professionals across the United States. Our content is designed by industry experts to keep professionals informed, compliant, and up to date with the latest codes, laws, and safety standards. Through our blog, we share practical insights, regulatory updates, and resources to support your professional growth and license renewal.
Disclaimer
The information provided in this educational content has been prepared with care to reflect current regulatory requirements for continuing education. However, licensing rules and regulations can vary by state and are subject to change. While we strive for accuracy, ExpertCE cannot guarantee that all details are complete or up to date at the time of reading. For the most current and authoritative information, always refer directly to your state’s official licensing board or regulatory agency.




 Login with Google
Login with Google